Gigawatt Farm
255.34 MW storage in Kern, CA · In queue since April 2023 · Proposed COD February 2030
255.34 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-01
Gigawatt Farm is a proposed 255.34 MW battery storage project located in Kern County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-55047, with a queue entry date of April 17, 2023. The proposed commercial operation date is February 1, 2030. As of the latest data, the interconnection agreement (IA) status is "Not Started". The project's point of interconnection (POI) is CALIENTE SW STA-MIDWAY #1, and it is within the Pacific Gas and Electric (PGAE) service area.
The Gigawatt Farm project has been the subject of recent news coverage, with nine articles published across industry, grid, and regulatory categories.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
CALIENTE SW STA-MIDWAY #1
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.