KETTLEMAN SOLAR PROJECT (FKA KETTLEMAN SOLAR FARM)
40 MW hybrid in Kings, CA · In queue since May 2010 · Proposed COD April 2025
40 MW
Capacity
2
Components
Solar + Battery
16 years
In Queue
IA Executed
IA Status
Signed Oct 2012
Queue → IA
2y 5m
IA → COD
12y 6m
Total Duration
2y 5m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-04-01
The Kettleman Solar Project (FKA Kettleman Solar Farm) is a proposed 40 MW hybrid solar and battery energy storage project located in Kings County, California. The project, under development in the CAISO region, consists of 20 MW of solar generation and 20 MW of battery storage. The proposed project is interconnected to the PG&E utility grid at the Henrietta-Tulare Lake 70 kV point of interconnection.
The project is listed in the CAISO interconnection queue as entry CAISO-625, with an original queue entry date of May 14, 2010. The proposed commercial operation date is April 1, 2025. An Interconnection Agreement (IA) for the project has been executed as of October 17, 2012. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kings
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Henrietta-Tulare Lake 70 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about KETTLEMAN SOLAR PROJECT (FKA KETTLEMAN SOLAR FARM)