NORTH ROSAMOND SOLAR
253 MW hybrid in Kern, CA · In queue since July 2010 · Proposed COD June 2026
253 MW
Capacity
2
Components
Solar + Battery
15y 10m
In Queue
IA Executed
IA Status
Signed Dec 2014
Queue → IA
4y 5m
IA → COD
11y 6m
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-06-01
The North Rosamond Solar project is a proposed 253 MW hybrid solar and battery energy storage project in Kern County, California. The development project consists of a 153 MW solar component and a 100 MW battery energy storage system. It is located within the CAISO region and interconnects with Southern California Edison (SCE) at the Whirlwind Sub 230 kV Bus.
The project, listed in the CAISO interconnection queue as CAISO-643R, entered the queue on July 31, 2010, and has a proposed commercial operation date of June 1, 2026. The Interconnection Agreement (IA) was executed on December 11, 2014. The North Rosamond Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Whirlwind Sub 230 kV Bus
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26