LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECT (CAISO-72) — Project Summary

Queue ID
CAISO-72
Capacity
500 MW
Technology
Battery
Status
active
Location
Riverside, CA
Region
CAISO
Developer
IA Status
IA Executed

LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECT

CAISO-72BetaActivePumped StorageCAISOLBNL + Live

500 MW storage in Riverside, CA · In queue since June 2005 · Proposed COD December 2028

500 MW

Capacity

1

Components

Pumped Storage

20y 11m

In Queue

IA Executed

IA Status

Signed Aug 2012

Interconnection

Queue → IA

7y 2m

IA → COD

16y 4m

Total Duration

7y 2m

Construction75%
Queue EntryJun 21, 2005

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementAug 11, 2012

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-12-31

About

The Lake Elsinore Advanced Pumped Storage Project is a proposed 500 MW pumped storage development in Riverside County, California. The project is located within the CAISO region and is interconnected with San Diego Gas & Electric (SDGE). It entered the CAISO interconnection queue as queue ID CAISO-72 on June 21, 2005, with a proposed commercial operation date of December 31, 2028.

The project's Interconnection Agreement (IA) was executed on August 11, 2012. The point of interconnection (POI) is the proposed Lee Lake Substation at 500 kV. The Lake Elsinore Advanced Pumped Storage Project has been the subject of recent news coverage related to regulatory matters.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Riverside

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SDGE

Entity

CAISO

Service Type

Point of Interconnection

Proposed Lee Lake Substation 500 kV

Data Source

LBNL + Live

ApplicantNevada Hydro Corp.The Press-Enterprise · 2023-05-19
AgencyFederal Energy Regulatory CommissionThe Press-Enterprise · 2023-05-19
RulingDenialThe Press-Enterprise · 2023-05-19
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SPCJCT_1_B1
POI Substation
Lee

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-31