CLPT-CLPT G24
200 MW generation in Laramie, WY · In queue since February 2023 · Proposed COD December 2026
200 MW
Capacity
1
Components
Wind
3y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The proposed CLPT-CLPT G24 project is a 200 MW wind generation facility located in Laramie County, Wyoming. The project is being developed by CLPT and is interconnected to the Black Hills Cheyenne Light Fuel and Power Transmission system at the Sweetgrass 230 kV Substation.
The project is currently in the Facility Study phase of the interconnection process within the utility's queue, having entered the queue on February 20, 2023. The proposed commercial operation date is December 1, 2026.
Generated from interconnection queue and public data sources
State
WY
County
Laramie
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Service Type
—
Point of Interconnection
Sweetgrass 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project CLPT-CLPT G24