CLPT-CLPT G31
130 MW generation in Laramie, WY · In queue since May 2024 · Proposed COD January 2029
130 MW
Capacity
1
Components
Gas
2 years
In Queue
Cluster Study
IA Status
COD target: 2029
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-01
The proposed CLPT-CLPT G31 project is a 130 MW gas-fired generation facility located in Laramie County, Wyoming. Developed by Cheyenne Light, Fuel & Power, the project is interconnected with Black Hills Cheyenne Light Fuel and Power Transmission. It entered the transmission provider's interconnection queue on May 30, 2024, with a proposed commercial operation date of January 1, 2029. Its interconnection status is currently in the Cluster Study phase.
The project has been the subject of recent news coverage, with three articles focusing on regulatory aspects.
Generated from interconnection queue and public data sources
State
WY
County
Laramie
Grid Region
Mountain West
Market
—
Developer
Cheyenne Light, Fuel & Power
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Service Type
—
Point of Interconnection
Cheyenne Prairie Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14