CSU-CSU-2020-1
175 MW generation in El Paso, CO · In queue since July 2020 · Proposed COD October 2023
175 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-10-31
The proposed CSU-CSU-2020-1 project is a 175 MW solar generation project located in El Paso County, Colorado. The project is being developed by Colorado Springs Utilities (CSU). It is currently active in the Colorado Springs Utilities interconnection queue, with an entry date of July 6, 2020, and a proposed commercial operation date of October 31, 2023.
The project has an Interconnection Agreement (IA) executed. The point of interconnection (POI) is the Williams Creek Substation. The project has appeared in recent news coverage regarding Colorado Springs Utilities' renewable energy expansion plans.
Generated from interconnection queue and public data sources
State
CO
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Service Type
—
Point of Interconnection
Williams Creek Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project CSU-CSU-2020-1