CSU-CSU-2020-3
200 MW hybrid in El Paso, CO · In queue since June 2020 · Proposed COD September 2025
200 MW
Capacity
1
Components
Solar
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
5y 3m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
CSU-CSU-2020-3 is a proposed 200 MW hybrid solar and battery project located in El Paso County, Colorado. The development project, located in the West region, is being proposed by Colorado Springs Utilities (CSU). The project consists of 200 MW of solar generation, coupled with battery storage.
The project is currently active in the Colorado Springs Utilities (CSU) interconnection queue, with an entry date of June 20, 2020. The proposed commercial operation date is September 1, 2025. The interconnection request is currently in the System Impact Study phase. The point of interconnection is the Williams Creek Substation.
Generated from interconnection queue and public data sources
State
CO
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Service Type
—
Point of Interconnection
Williams Creek Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project CSU-CSU-2020-3