CSU-CSU-2021-2
500 MW generation in Lincoln, CO · In queue since July 2021 · Proposed COD December 2025
500 MW
Capacity
1
Components
Wind
4y 10m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
4y 5m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed CSU-CSU-2021-2 project is a 500 MW wind generation facility located in Lincoln County, Colorado. The developer is Colorado Springs Utilities (CSU). It is currently active in the Colorado Springs Utilities interconnection queue, with an entry date of July 16, 2021, and a proposed commercial operation date of December 31, 2025.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is Williams Creek. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Service Type
—
Point of Interconnection
Williams Creek
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project CSU-CSU-2021-2