CSU-CSU-2022-2
100 MW generation in El Paso, CO · In queue since September 2022 · Proposed COD January 2025
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
2y 4m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-01
The proposed CSU-CSU-2022-2 project is a 100 MW solar generation facility located in El Paso County, Colorado. The project is being developed by Colorado Springs Utilities (CSU). It consists of 100 MW of solar photovoltaic generation.
The project is currently in the Colorado Springs Utilities interconnection queue as of September 2, 2022, with a proposed commercial operation date of January 1, 2025. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Nixon Substation.
Generated from interconnection queue and public data sources
State
CO
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Service Type
—
Point of Interconnection
Nixon Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.