CSU-CSU-2022-3
200 MW hybrid in El Paso, CO · In queue since February 2023 · Proposed COD August 2026
200 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Feasibility Study
IA Status
COD target: 2026
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-01
CSU-CSU-2022-3 is a proposed 200 MW hybrid solar and battery project located in El Paso County, Colorado. The development project, under Colorado Springs Utilities (CSU), consists of 200 MW of solar capacity.
The project is currently active in the Colorado Springs Utilities interconnection queue (CSU) with a queue entry date of February 2, 2023, and a proposed commercial operation date of August 1, 2026. Its interconnection agreement status is currently in the Feasibility Study phase, and the point of interconnection is Williams Creek- Horizon Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Service Type
—
Point of Interconnection
Williams Creek- Horizon Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.