CSU-CSU-2023-3
300 MW generation in El Paso, CO · In queue since May 2023 · Proposed COD January 2026
300 MW
Capacity
1
Components
Solar
3 years
In Queue
Feasibility Study
IA Status
COD target: 2026
Total Duration
2y 8m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-11
The proposed CSU-CSU-2023-3 project is a 300 MW solar generation development in El Paso County, Colorado. The project is being developed by Colorado Springs Utilities (CSU). It consists of 300 MW of solar photovoltaic generation.
The project is currently in the Colorado Springs Utilities (CSU) interconnection queue as of May 8, 2023, with a proposed commercial operation date of January 11, 2026. Its interconnection status is currently in the Feasibility Study phase. The point of interconnection is the Williams Creek Substation.
Generated from interconnection queue and public data sources
State
CO
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Service Type
—
Point of Interconnection
Williams Creek Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.