Dominion-20230825002
2.5 MW generation in Aiken, SC · Proposed COD July 2024
2.5 MW
Capacity
1
Components
Solar
—
In Queue
—
IA Status
COD target: 2024
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-31
Dominion-20230825002 is a proposed solar generation project with a total capacity of 2.5 MW. The project is located in Aiken County, South Carolina, within the service territory of Dominion Energy South Carolina. Dominion is the listed entity for the project.
The project is currently active in the Dominion Energy South Carolina interconnection queue, having entered the queue on August 25, 2023. The proposed commercial operation date is July 31, 2024. The point of interconnection is at the Aiken - Southeastern Clay 46 kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Aiken
Grid Region
Southeast
Market
—
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Service Type
—
Point of Interconnection
Aiken - Southeastern Clay 46 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Dominion-20230825002