Dominion-20230829005
47.7 MW generation in Lexington, SC · Proposed COD September 2023
47.7 MW
Capacity
1
Components
Hydro
—
In Queue
—
IA Status
COD target: 2023
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-01
Dominion-20230829005 is a proposed hydroelectric generation project with a total capacity of 47.7 MW. The development project is located in Lexington County, South Carolina, within the service territory of Dominion Energy South Carolina. The listed developer is DESC - Generation, an entity of Dominion.
The project is currently active in the Dominion Energy interconnection queue, with a queue entry date of August 29, 2023. The proposed commercial operation date is September 1, 2023, and the point of interconnection is the Saluda Hydro 115 kV Substation.
Generated from interconnection queue and public data sources
State
SC
County
Lexington
Grid Region
Southeast
Market
—
Developer
DESC - Generation
Utility
Dominion Energy South Carolina
Entity
Dominion
Service Type
—
Point of Interconnection
Saluda Hydro 115 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.