Dominion-20230829014
199 MW storage in Berkeley, SC · Proposed COD December 2028
199 MW
Capacity
1
Components
Battery
—
In Queue
—
IA Status
COD target: 2028
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Dominion-20230829014 is a proposed 199 MW battery storage project located in Berkeley County, South Carolina. The project is being developed by Dominion and is interconnected with Dominion Energy South Carolina. It consists of a single 199 MW battery component.
The project is currently active in the Dominion Energy South Carolina interconnection queue, having entered the queue on August 29, 2023. The proposed commercial operation date is December 1, 2028.
Generated from interconnection queue and public data sources
State
SC
County
Berkeley
Grid Region
Southeast
Market
—
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Service Type
—
Point of Interconnection
Williams - Goose Creek 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Dominion-20230829014