Dominion-20240829001
250 MW hybrid in Richland, SC · Proposed COD December 2028
250 MW
Capacity
1
Components
Solar
—
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-29
Dominion-20240829001 is a proposed 250 MW hybrid solar and battery energy storage project located in Richland County, South Carolina. The project, being developed by Dominion, consists of 250 MW of solar photovoltaic generation.
The project is currently active in the Dominion Energy South Carolina interconnection queue, with an entry date of August 29, 2024. The proposed commercial operation date is December 29, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
SC
County
Richland
Grid Region
Southeast
Market
—
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Service Type
—
Point of Interconnection
Wateree - Hopkins 230 kV #2
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Dominion-20240829001