Dominion-20240829018
150 MW generation in Lexington, SC · Proposed COD December 2027
150 MW
Capacity
1
Components
Solar
—
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-30
Dominion-20240829018 is a proposed solar generation project with a total capacity of 150 MW. The project is located in Lexington County, South Carolina, within the service territory of Dominion Energy South Carolina. Dominion is the entity associated with the project.
The project is currently active in the Dominion Energy South Carolina interconnection queue, with a queue entry date of August 29, 2024. The proposed commercial operation date is December 30, 2027. The interconnection agreement status is listed as "In Progress (unknown study)". Recent news coverage of the project exists.
Generated from interconnection queue and public data sources
State
SC
County
Lexington
Grid Region
Southeast
Market
—
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Service Type
—
Point of Interconnection
Edmund Switching Station - Owens Corning 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Dominion-20240829018