Duke-100
0.8 MW generation in Marion, FL · In queue since April 2009 · Proposed COD July 2009
0.8 MW
Capacity
1
Components
Other
17y 1m
In Queue
IA Executed
IA Status
COD target: 2009
Total Duration
3 months
Schedule
204 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2009-07-31
The proposed Duke-100 project is a 0.8 MW generation project located in Marion County, Florida. The project, developed by Duke Energy Florida, utilizes an unspecified "Other" technology. It entered the Duke Energy Florida interconnection queue on April 15, 2009, with a proposed commercial operation date of July 31, 2009.
The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Marion
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-100