Duke-105
0.1 MW generation in Marion, FL · In queue since April 2010 · Proposed COD April 2010
0.1 MW
Capacity
1
Components
Other
16y 1m
In Queue
IA Executed
IA Status
COD target: 2010
Total Duration
<1 month
Schedule
196 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2010-04-12
Duke-105 is a proposed 0.1 MW generation project located in Marion County, Florida. The project, developed by Duke Energy Florida, utilizes an unspecified "Other" technology. It is interconnected to the Maricamp Substation.
The project is listed in the Duke Energy Florida interconnection queue as "Duke-105," with a queue entry date of April 12, 2010, and a proposed commercial operation date of April 12, 2010. The interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Marion
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Maricamp Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN