Duke-151
74.5 MW generation in Columbia, FL · In queue since July 2016 · Proposed COD May 2023
74.5 MW
Capacity
1
Components
Solar
9y 10m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
6y 10m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-19
Duke-151 is a proposed solar generation project with a total capacity of 74.5 MW, located in Columbia County, Florida. The developer is listed as Masked. The project is interconnected to Duke Energy Florida via the Radiant Switching Station 230 kV.
The project is currently in the Duke Energy Florida interconnection queue as "Duke-151", with an entry date of July 27, 2016. Its proposed commercial operation date is May 19, 2023, and its interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Columbia
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Radiant Switching Station 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-151