Duke-164382
37.5 MW generation in Laurens, SC · In queue since March 2020 · Proposed COD November 2026
37.5 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Construction
IA Status
COD target: 2026
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-30
Duke-164382 is a proposed solar generation project with a total capacity of 37.5 MW. The project is located in Laurens County, South Carolina, within the Duke Energy Carolinas service area. Duke is listed as the entity associated with the project.
The project is currently active in the Duke Energy Carolinas interconnection queue, with an entry date of March 6, 2020. The proposed commercial operation date is November 30, 2026, and the interconnection agreement status is listed as "Construction". The point of interconnection is the Clinton WH 100kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Laurens
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Clinton WH 100kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.