Duke-165
74.5 MW generation in Polk, FL · In queue since December 2016 · Proposed COD December 2018
74.5 MW
Capacity
1
Components
Solar
9y 5m
In Queue
Suspended
IA Status
COD target: 2018
Total Duration
2 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-12-31
Duke-165 is a proposed solar generation project located in Polk County, Florida, with a total capacity of 74.5 MW. The project, developed by Wild Turkey Solar, LLC, is interconnected with Duke Energy Florida via the Catfish Switching Station 230 kV. It entered the Duke interconnection queue on December 21, 2016, with a proposed commercial operation date of December 31, 2018.
The interconnection agreement (IA) status for the project is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
Wild Turkey Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Catfish Switching Station 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN