Duke-166
74.5 MW generation in Hamilton, FL · In queue since December 2016 · Proposed COD May 2023
74.5 MW
Capacity
1
Components
Solar
9y 5m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
6y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-26
Duke-166 is a proposed solar generation project with a total capacity of 74.5 MW, located in Hamilton County, Florida. The project, developed by Florida Renewable Partners, LLC, is interconnected with Duke Energy Florida via the Suwannee Springs Substation 115 kV. It is listed in the Duke Energy interconnection queue with a queue entry date of December 21, 2016, and a proposed commercial operation date of May 26, 2023.
The interconnection agreement (IA) status for the project is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Hamilton
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Suwannee Springs Substation 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-166