Duke-186466
50 MW storage in Gaston, NC · In queue since July 2021 · Proposed COD December 2025
50 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
4y 5m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-12-01
Duke-186466 is a proposed 50 MW battery storage project located in Gaston County, North Carolina. The project, developed by Duke Energy Carolinas, is interconnected to the Duke Energy Carolinas system. It entered the interconnection queue on July 6, 2021, and has a proposed commercial operation date of December 1, 2025.
The project's interconnection agreement has been executed. It is interconnected at the Allen BL 100kV point of interconnection. The project has appeared in recent news coverage regarding Duke Energy's battery storage buildout plans.
Generated from interconnection queue and public data sources
State
NC
County
Gaston
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Allen BL 100kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-186466