Project Duke-20832 — Project Summary

Queue ID
Duke-20832
Capacity
2 MW
Technology
Solar
Status
active
Location
Marion, SC
Region
Southeast
Developer
IA Status
Construction

Duke-20832

Duke-20832BetaActiveSolarDukeLBNL

2 MW generation in Marion, SC · In queue since May 2018 · Proposed COD September 2024

2 MW

Capacity

1

Components

Solar

8 years

In Queue

Construction

IA Status

COD target: 2024

Interconnection

Total Duration

6y 4m

Schedule

20 months past proposed COD

In Study38%
Queue EntryMay 9, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-02

About

Duke-20832 is a proposed solar generation project with a total capacity of 2 MW, located in Marion County, South Carolina. The project is being developed by Duke and is interconnected to Duke Energy Progress via the Mullins 115kV point of interconnection.

The project is listed as active in the Duke Energy Progress interconnection queue, with an entry date of May 9, 2018, and a proposed commercial operation date of September 2, 2024. Its interconnection agreement status is currently listed as "Construction".

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Marion

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Progress

Entity

Duke

Service Type

Point of Interconnection

Mullins 115kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project Duke-20832