Duke-225
74.5 MW generation in Gilchrist, FL · In queue since April 2018 · Proposed COD January 2023
74.5 MW
Capacity
1
Components
Solar
8y 1m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-13
Duke-225 is a proposed solar generation project with a total capacity of 74.5 MW, located in Gilchrist County, Florida. The project, developed by Florida Renewable Partners, LLC, is interconnected to Duke Energy Florida via the Newberry Substation at 230 kV.
The project is listed in the Duke Energy Florida interconnection queue with an entry date of April 20, 2018. The proposed commercial operation date was January 13, 2023, but the interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Gilchrist
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Newberry Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.