Duke-237
74.5 MW generation in Pasco, FL · In queue since July 2018 · Proposed COD January 2024
74.5 MW
Capacity
1
Components
Solar
7y 10m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-01-19
Duke-237 is a proposed solar generation project located in Pasco County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Renewable Partners, LLC, is interconnected with Duke Energy Florida via the Trilby Substation 69 kV. It entered the Duke Energy queue on July 17, 2018, with a proposed commercial operation date of January 19, 2024.
The interconnection status of the project is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Pasco
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Trilby Substation 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-237