Duke-238
74.5 MW generation in Taylor, FL · In queue since August 2018 · Proposed COD August 2023
74.5 MW
Capacity
1
Components
Solar
7y 9m
In Queue
IA Pending
IA Status
COD target: 2023
Total Duration
5 years
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-28
Duke-238 is a proposed solar generation project located in Taylor County, Florida, with a total capacity of 74.5 MW. The developer is listed as Masked, and the interconnecting utility is Duke Energy Florida. This project is in the Duke Energy interconnection queue with an entry date of August 7, 2018.
The proposed commercial operation date for Duke-238 is August 28, 2023, and its interconnection agreement (IA) status is currently listed as "IA Pending". The point of interconnection (POI) is the Perry Substation at 69 kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
FL
County
Taylor
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Perry Substation 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.