Duke-24
70 MW generation in Polk, FL · In queue since June 2005 · Proposed COD June 2011
70 MW
Capacity
1
Components
Other
20y 11m
In Queue
IA Executed
IA Status
COD target: 2011
Total Duration
6 years
Schedule
182 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2011-06-01
Duke-24 is a proposed 70 MW generation project located in Polk County, Florida. The project, developed by NorthernStar, is interconnected with Duke Energy Florida at the Vandolah Substation. The technology is listed as "Other".
The project is in the Duke Energy Florida interconnection queue as of June 7, 2005, with a proposed commercial operation date of June 1, 2011. The interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
NorthernStar
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Vandolah Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-24