Duke-242
74.9 MW generation in Hernando, FL · In queue since November 2018 · Proposed COD May 2025
74.9 MW
Capacity
1
Components
Solar
7y 6m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
6y 6m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-10
Duke-242 is a proposed solar generation project with a total capacity of 74.9 MW, located in Hernando County, Florida. The project is being developed by Duke Energy Florida, LLC and is interconnected with Duke Energy Florida. It entered the queue on November 14, 2018, and has a proposed commercial operation date of May 10, 2025. The interconnection agreement status is currently listed as "Construction".
The point of interconnection for Duke-242 is the Nobleton Substation Or Brooksville - Inverness 69 kV. The project has appeared in recent news coverage regarding Duke Energy's solar expansion plans in Florida.
Generated from interconnection queue and public data sources
State
FL
County
Hernando
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Nobleton Substation Or Brooksville - Inverness 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.