Duke-251
74.5 MW generation in Gadsden, FL · In queue since April 2019 · Proposed COD December 2021
74.5 MW
Capacity
1
Components
Solar
7y 1m
In Queue
Suspended
IA Status
COD target: 2021
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
Duke-251 is a proposed solar generation project with a total capacity of 74.5 MW, located in Gadsden County, Florida. The developer is Apalachicola Solar, LLC, and the interconnecting utility is Duke Energy Florida. The project entered the Duke Energy queue on April 1, 2019, with a proposed commercial operation date of December 31, 2021.
The interconnection agreement (IA) status for Duke-251 is currently listed as Suspended. The point of interconnection (POI) is the Atwater - Liberty 115 kV line. The project has also been listed as having a suspended status in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Gadsden
Grid Region
Southeast
Market
—
Developer
Apalachicola Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Atwater - Liberty 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN