Duke-258
74.9 MW generation in Highlands, FL · In queue since May 2019 · Proposed COD October 2022
74.9 MW
Capacity
1
Components
Solar
7 years
In Queue
Construction
IA Status
COD target: 2022
Total Duration
3y 5m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-28
Duke-258 is a proposed 74.9 MW solar generation project located in Highlands County, Florida. The project, developed by Placid Solar, LLC, is interconnected to Duke Energy Florida via the Fisheating Creek Substation 230 kV. It entered the Duke interconnection queue on May 31, 2019, with a proposed commercial operation date of October 28, 2022. The project's interconnection status is currently listed as "Construction".
The development project consists of 74.9 MW of solar photovoltaic generation. It is located in the Southeast region and is listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Highlands
Grid Region
Southeast
Market
—
Developer
Placid Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Fisheating Creek Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-258