Duke-269
74.9 MW generation in Marion, FL · In queue since September 2019 · Proposed COD March 2024
74.9 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
4y 6m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-01
Duke-269 is a proposed solar generation project with a total capacity of 74.9 MW, located in Marion County, Florida. The project is being developed by a masked developer and is interconnected with Duke Energy Florida. It entered the Duke Energy queue on September 20, 2019, and has a proposed commercial operation date of March 1, 2024. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection for Duke-269 is the Dunnellon Town Substation at 69 kV. The project has appeared in recent news coverage regarding renewable energy development in Florida.
Generated from interconnection queue and public data sources
State
FL
County
Marion
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Dunnellon Town Substation 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-269