Duke-27
223 MW generation in Pinellas, FL · In queue since September 2005 · Proposed COD December 2008
223 MW
Capacity
1
Components
Other
20y 8m
In Queue
IA Executed
IA Status
COD target: 2008
Total Duration
3y 3m
Schedule
212 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2008-12-01
Duke-27 is a proposed 223 MW generation project located in Pinellas County, Florida. The project, developed by Duke Energy Florida, LLC, utilizes an unspecified "Other" technology. It is interconnected to the Duke Energy Florida system at the Bartow Substation.
The project entered the Duke interconnection queue on September 13, 2005, with a proposed commercial operation date of December 1, 2008. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Pinellas
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Bartow Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.