Duke-273
74.9 MW generation in Polk, FL · In queue since December 2019 · Proposed COD October 2022
74.9 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Suspended
IA Status
COD target: 2022
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-28
Duke-273 is a proposed solar generation project located in Polk County, Florida, with a total capacity of 74.9 MW. The project, under development by FL Solar 10, LLC, is interconnected to the Duke Energy Florida system at the Tiger Bay Substation 230 kV.
The project entered the Duke interconnection queue on December 17, 2019, with a proposed commercial operation date of October 28, 2022. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
FL Solar 10, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Tiger Bay Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-273