Project Duke-273 — Project Summary

Queue ID
Duke-273
Capacity
74.9 MW
Technology
Solar
Status
suspended
Location
Polk, FL
Region
Southeast
Developer
FL Solar 10, LLC
IA Status
Suspended

Duke-273

Duke-273BetaSuspendedSolarDukeLBNL

74.9 MW generation in Polk, FL · In queue since December 2019 · Proposed COD October 2022

74.9 MW

Capacity

1

Components

Solar

6y 5m

In Queue

Suspended

IA Status

COD target: 2022

Interconnection

Total Duration

2y 10m

Suspended38%
Queue EntryDec 17, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-28

About

Duke-273 is a proposed solar generation project located in Polk County, Florida, with a total capacity of 74.9 MW. The project, under development by FL Solar 10, LLC, is interconnected to the Duke Energy Florida system at the Tiger Bay Substation 230 kV.

The project entered the Duke interconnection queue on December 17, 2019, with a proposed commercial operation date of October 28, 2022. Its interconnection agreement status is currently listed as suspended.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Polk

Grid Region

Southeast

Market

Developer

FL Solar 10, LLC

Utility

Duke Energy Florida

Entity

Duke

Service Type

Point of Interconnection

Tiger Bay Substation 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.