Duke-277
74.9 MW generation in Alachua, FL · In queue since March 2020 · Proposed COD July 2025
74.9 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
5y 4m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-31
Duke-277 is a proposed solar generation project located in Alachua County, Florida, with a total capacity of 74.9 MW. The developer is FL Solar 8, LLC, and the interconnecting utility is Duke Energy Florida.
The project is listed in the Duke Energy queue with an entry date of March 6, 2020, and a proposed commercial operation date of July 31, 2025. Its interconnection agreement status is currently listed as "Construction". The point of interconnection is the Sunrise Switching Station at 69 kV.
Generated from interconnection queue and public data sources
State
FL
County
Alachua
Grid Region
Southeast
Market
—
Developer
FL Solar 8, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Sunrise Switching Station 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-277