Duke-284
74.5 MW generation in Alachua, FL · In queue since April 2020 · Proposed COD December 2021
74.5 MW
Capacity
1
Components
Solar
6y 1m
In Queue
Suspended
IA Status
COD target: 2021
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
Duke-284 is a proposed solar generation project located in Alachua County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Renewable Partners, LLC, is interconnected with Duke Energy Florida via the Archer Substation 230 kV.
The project is listed in the Duke Energy interconnection queue with an entry date of April 21, 2020, and a proposed commercial operation date of December 31, 2021. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Alachua
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Archer Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-284