Duke-286
74.5 MW generation in Gilchrist, FL · In queue since May 2020 · Proposed COD December 2022
74.5 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
2y 7m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
Duke-286 is a proposed solar generation project with a total capacity of 74.5 MW, located in Gilchrist County, Florida. The development project is being pursued by a masked developer and is interconnected with Duke Energy Florida. It entered the Duke Energy interconnection queue on May 29, 2020, with a proposed commercial operation date of December 31, 2022.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Hayfield Substation at 230 kV.
Generated from interconnection queue and public data sources
State
FL
County
Gilchrist
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Hayfield Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-286