Duke-290
74.9 MW generation in Suwannee, FL · In queue since December 2020 · Proposed COD October 2023
74.9 MW
Capacity
1
Components
Solar
5y 5m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
2y 10m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
Duke-290 is a proposed solar generation project with a total capacity of 74.9 MW, located in Suwannee County, Florida. The project is being developed by a masked developer and is interconnected with Duke Energy Florida. It is currently in the Duke Energy Florida interconnection queue with an entry date of December 30, 2020.
The proposed commercial operation date for Duke-290 is October 31, 2023. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Chariot Switching Station 115 kV.
Generated from interconnection queue and public data sources
State
FL
County
Suwannee
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Chariot Switching Station 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN