Duke-292
225 MW storage in Pinellas, FL · In queue since March 2021 · Proposed COD May 2025
225 MW
Capacity
1
Components
Battery
5y 2m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-31
Duke-292 is a proposed 225 MW battery storage project located in Pinellas County, Florida. The project, developed by Duke Energy Florida, LLC, entered the Duke Energy Florida interconnection queue on March 31, 2021, with a proposed commercial operation date of May 31, 2025. The point of interconnection is the Bartow Plant Substation at 230 kV.
The interconnection agreement status for Duke-292 is currently listed as suspended. Recent news coverage has discussed the project in relation to Duke Energy's broader energy storage plans in Florida.
Generated from interconnection queue and public data sources
State
FL
County
Pinellas
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Bartow Plant Substation 230 kV