Duke-293
74.9 MW generation in Alachua, FL · In queue since August 2021 · Proposed COD September 2024
74.9 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
Duke-293 is a proposed solar generation project located in Alachua County, Florida. The project, with a total capacity of 74.9 MW, is being developed by Pleasant Solar, LLC, and is interconnected with Duke Energy Florida. It entered the Duke interconnection queue on August 4, 2021, with a proposed commercial operation date of September 30, 2024.
The interconnection agreement (IA) for Duke-293 is currently listed as suspended. Recent news coverage has discussed the project's progress and potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
State
FL
County
Alachua
Grid Region
Southeast
Market
—
Developer
Pleasant Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Highsprings to Hull Road 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-293