Duke-307
74.9 MW generation in Suwannee, FL · In queue since April 2022 · Proposed COD October 2025
74.9 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
Duke-307 is a proposed solar generation project with a total capacity of 74.9 MW, located in Suwannee County, Florida. The developer is CP Ironwood, LLC, and the interconnecting utility is Duke Energy Florida. The project consists of 74.9 MW of solar photovoltaic generation.
The project is in the Duke Energy Florida interconnection queue (Duke) as entry Duke-307, with a queue entry date of April 15, 2022. The proposed commercial operation date is October 1, 2025. The interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Suwannee
Grid Region
Southeast
Market
—
Developer
CP Ironwood, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Ft White - Suwannee River 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-307