Duke-308
74.9 MW generation in Suwannee, FL · In queue since April 2022 · Proposed COD October 2025
74.9 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
State
FL
County
Suwannee
Grid Region
Southeast
Market
—
Developer
CP Ironwood, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Ft White - Suwannee River 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-308