Duke-312
74.5 MW generation in Alachua, FL · In queue since April 2022 · Proposed COD June 2024
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
Duke-312 is a proposed solar generation project with a total capacity of 74.5 MW, located in Alachua County, Florida. The developer is Florida Renewable Partners, LLC, and the interconnecting utility is Duke Energy Florida. The project entered the Duke interconnection queue on April 18, 2022, with a proposed commercial operation date of June 1, 2024.
The interconnection agreement (IA) status for Duke-312 is currently listed as suspended. The point of interconnection (POI) is the Bronson - Newberry 230 kV line.
Generated from interconnection queue and public data sources
State
FL
County
Alachua
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Bronson - Newberry 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.