Duke-314
74.5 MW generation in Levy, FL · In queue since August 2022 · Proposed COD June 2027
74.5 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Construction
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-14
Duke-314 is a proposed 74.5 MW solar generation project located in Levy County, Florida. The project, under development by Florida Renewable Partners, LLC, is interconnected with Duke Energy Florida via the Sunset Switching Station 230 kV. It entered the Duke interconnection queue on August 11, 2022, with a proposed commercial operation date of June 14, 2027. The project's interconnection agreement status is currently listed as "Construction".
The proposed project consists of 74.5 MW of solar photovoltaic generation. It is currently listed as an active project within the Duke interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in Florida.
Generated from interconnection queue and public data sources
State
FL
County
Levy
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Sunset Switching Station 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.