Duke-315
74.5 MW generation in Levy, FL · In queue since August 2022 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Construction
IA Status
COD target: 2026
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
The proposed Duke-315 project is a 74.5 MW solar generation facility located in Levy County, Florida. Developed by Florida Renewable Partners, LLC, the project is interconnected with Duke Energy Florida via the Sunset Switching Station at 230 kV.
The project is currently active in the Duke Energy Florida interconnection queue, with an entry date of August 11, 2022, and a proposed commercial operation date of December 30, 2026. The interconnection agreement status is listed as "Construction".
Generated from interconnection queue and public data sources
State
FL
County
Levy
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Sunset Switching Station 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-315