Duke-318
8 MW storage in Suwannee, FL · In queue since November 2022 · Proposed COD December 2024
8 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Construction
IA Status
COD target: 2024
Total Duration
2y 1m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
Duke-318 is a proposed 8 MW battery storage project located in Suwannee County, Florida. The project, being developed by Duke Energy Florida, LLC, entered the Duke Energy Florida interconnection queue on November 19, 2022. The proposed commercial operation date is December 31, 2024, and the project's interconnection agreement status is currently listed as "Construction".
The project consists of 8 MW of battery storage capacity. It is interconnected at the Suwannee 230 kV Substation.
Generated from interconnection queue and public data sources
State
FL
County
Suwannee
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Suwannee 230 kV Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.