Duke-319
74.9 MW generation in Hernando, FL · In queue since November 2022 · Proposed COD June 2025
74.9 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
Duke-319 is a proposed solar generation project located in Hernando County, Florida, with a total capacity of 74.9 MW. The project is being developed by Duke Energy Florida, LLC, and is interconnected to the Duke Energy Florida utility.
The project entered the Duke Energy interconnection queue on November 29, 2022, with a proposed commercial operation date of June 1, 2025. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Hernando
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Brooksville-Bushnell East 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.