Duke-320
74.9 MW generation in Hernando, FL · In queue since November 2022 · Proposed COD June 2026
74.9 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
Duke-320 is a proposed solar generation project located in Hernando County, Florida, with a total capacity of 74.9 MW. The project, developed by Duke Energy Florida, LLC, entered the Duke Energy Florida interconnection queue on November 29, 2022, and has a proposed commercial operation date of June 1, 2026. The interconnection agreement status is currently listed as suspended.
The point of interconnection for Duke-320 is the Brooksville-Bushnell East 230 kV line. The project's status in the interconnection queue is also listed as suspended.
Generated from interconnection queue and public data sources
State
FL
County
Hernando
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Brooksville-Bushnell East 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.