74.5 MW generation in Gilchrist, FL · In queue since February 2023 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Duke-324 is a proposed solar generation project located in Gilchrist County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Renewable Partners, LLC, is interconnected with Duke Energy Florida via the Hayfield Substation 230 kV. It entered the Duke Energy interconnection queue on February 20, 2023, with a proposed commercial operation date of December 31, 2026. Its interconnection agreement status is currently suspended.
The project consists of 74.5 MW of solar photovoltaic generation. The project's interconnection agreement is also currently suspended.
Generated from interconnection queue and public data sources
State
FL
County
Gilchrist
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Hayfield Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-324